As of September 2024
Ongoing Works:
Excavation Works: Completed
Civil/ Structural/ Architectural Works:
Substantially Completed
Interior painting works for Clusters I, G,
F and Podium
Mechanical Works: Installation of refrigerant pipe and
condensate drain at Clusters F and E
Electrical Work: Installation of devices at Clusters I, G,
and F
Plumbing/ Sanitary: Installation of riser at Cluster E
Fire Protection: Installation of droppings at Cluster
G, F, and E
Aerial Shots
Exterior Painting
Ceiling Works at hallway and lift lobby at 15F – 17F
Ceiling Works and Dry Wall at Cluster G 17F
Ceiling Works and Drywall at Cluster F 19F Hallway Works