SunnyCoast Residential Resort

Construction Updates

Excavation

As of November 2024

Ongoing Works:

Civil/Structrual/Achitectural Works

• Concrete pouring at
18/F-19/F Tower 1
• Masonry works at 3/F – 20/F

Mechanical Works

• Ducting works at 3/F Tower 2

Electrical & Auxiliary Works

• Installation of roughing-ins at
3/F – 19/F Tower 1 and
3/F-21/F Tower 2

Sanitary & Plumbing Works

• Installation and layout of piping
works at 3/F-19/F Tower 1 and
3/F-21/F Tower 2

Fire Protection Works

• Ongoing installation of fire
protection pipes for Fire
Department connection at LG/F

Progress Photo

Facade

Balcony Railing and ACCU Installation

Slab Electrical Roughing Ins

Rebar Installation

                                                    Precast Fabrication                                                                                                                             Formworks

Precast Installation

3F Residential Units

7F Residential Units

15F Residential Units