Grand Westside Hotel

Construction Updates

Excavation

As of June 2022

Piling Works

  • Completed.

Civil/Structural Works

  • Ongoing concreting works at podium

Architectural Works

  • Ongoing guestroom painting works at South Tower 5th to 7th Floor

Mechanical Works

  • Ongoing pipe sleeving works and pipe installation at guestroom units at South and North Tower

Electrical and Auxiliary

  • Ongoing wiring works for ceiling closure of guestroom units at 7th Floor South Tower Plumbing/ Sanitary
  • Ongoing piping works and riser installation at 5th to 12th Floor South Tower Fire Protection
  • Ongoing fire protection riser installation at Fire Exit 1, 4 and 5

Excavation, Civil Works, Building Top-off, Start of Glass Installation

As of December 2023

Piling Works

  • Completed.

Structural/Civil Works

  • Ongoing CHB laying at NT 18/F-20/F

Architectural Works

  • Ongoing guestroom wall and ceiling framing works at ST 16/F- 18/F

Mechanical Works

  • Ongoing mechanical ducting works at ST 6/F-7/F guestroom units

Electrical and Auxiliary

  • Ongoing completion of roughing-ins for electrical & auxiliary at ST and NT

Plumbing/ Sanitary

  • Ongoing completion of waterline installation at ST 17/F and NT 12/F

Fire Protection

  • Ongoing installation of riser at ST 8/F-12/F