SunnyCoast Residential Resort

Construction Updates

Excavation

As of June 2024

Ongoing Works:

Site Preparation/Civil/Structural Works

• Ongoing concrete pouring at 19/F Tower 2
• Ongoing rubbed concrete finishing at 2/F-11/F

Mechanical Works

• Ongoing refrigerant and ducting works at UG/F-6/F

Electrical & Auxiliary Works

• Ongoing Installation of roughing-ins at 3/F-11/F Tower 1 and 3/F-19/F Tower 2

Sanitary & Plumbing Works

• Installation and layout piping works at  3/F-11/F Tower 1 and 

Fire Protection Works

• Ongoing installation of fire protection pipes for FDC at LG/F

Progress Photo

Facade

Concrete Pouring

Masonry Works at Lower Ground Floor 

Balcony and ACCU Installation